Turf Work: Terms in San Mamés

Turf Work: Terms in San Mamés

Following, we enclose the work plan that the company Cengotita has estimated for the substitution…

Following, we enclose the work plan that the company Cengotita has estimated for the substitution of the turf in San Mamés; in which days of work are mentioned:

*Excavation and removal of materials: 4 days.
*Levelling of the base: 2 days.
*Installation of the automatic irrigation network: 2 days.
*Application of drainage material: 1 day.
*Stocking, spreading and levelling of the root layer: 3 days.
*Installation of the new drainage system: 3 days.
*Installation of the new collector system: 1 day.
*Preparation of the land for the positioning of the sod: 1 day.
*Laying of the sod: 3 days.